Royal High School’s stadium proudly welcomes home games for the rest of the year with the opening of the new track and field.
Under construction for about six months–about two months longer than first scheduled to accommodate some project additions–the new synthetic turf field and new track were celebrated at a ribbon cutting ceremony Monday night by students, staff and parents. The ceremony was part of the Future Highlander Night that the school hosts every spring to introduce prospective students to the school’s athletic programs and honor the school’s senior athletes who have signed their Letters of Intent for college.
The $2 million project originally included only the replacement of the field’s turf and the resurfacing of the track. But because the project went out to competitive bid and came in with a price tag less than expected (about $1.85 million), the Simi Valley Unified School District School Board approved the addition of replacing the entire track as well, said Bond Manager Anthony Joseph.

“I think we saved several hundred thousand dollars by this bidding process,” Joseph said. “We just would not have had the money without this starting point.”
Competitive bids for the original project from five bidders ranged from $1.85 to $2.5 million, Joseph said.
The project’s money came from the Measure C4 Bond, which was passed by voters in 2004 and paid for facility and technology upgrades throughout the SVUSD. With most of the bond’s $145 million spent, this is likely the last large-scale project to be done on one site, though there are several remaining projects at various school sites scheduled for the near future.

Since the bond’s passage, every SVUSD campus has received facility improvements and technology upgrades. Bigger projects include the Performing Arts Building at Santa Susana High School, the stadiums at both Simi Valley and Royal high schools, extensive infrastructure improvements to utilities at all campuses, WiFi at every campus, the launch of the first phase of the District’s technology plan, which includes iPad and ChromeBook pilot programs, computer labs at all schools, new roofs, new air conditioning and heating units in aging campuses and much more.
“We’d like to thank all of you, as a community, for passing the bond that allowed us to do this project,” said Royal Principal Keith Derrick.
The Royal field project encountered delays from the addition of the new track and the discovery that the stadium’s lighting system needed to be relaid under the track and field, said Joseph, which pushed the completion date out about two months.

But on Monday, with the bright green turf and red track shining proudly under the setting sun, only praise could be heard for the project’s success.
“I firmly believe that our students deserve not only the best in instruction, but also in facilities,” said District Superintendent Jason Peplinski at Monday’s ceremony. “And we now have a field…that is worthy of our students’ talents and efforts.”